|
January to April 2005 with
launch on Friday 8th April
Remainder of construction went well. Wish I hadn’t
attacked the sheer capping with the electric planer as it is very difficult
to get a consistent edge. Job for next winter to tidy up.
We attempted to cast the bulb keel
ourselves however this didn’t work due to inability to melt the lead in
sufficiently large enough quantities so we had to resort to professional
casting using our plug, the cost seemed very high. Fitting the bulb was
approached with trepidation however it proved quite straightforward as once
the bulb halves were crow barred onto the ground from the trailer they could
be moved around quite easily by rocking and walking on the curved side. Use
of a ladder against the hull side and a chain hoist saw the bulb halves
lifted onto a temporary platform then walked the bulb up to the keel and
tipped into upright position by use of jacks under the platform. Bolts holes
lined up fine as we had drilled them by sliding the keel under the bulb half
whilst on the trailer and drilling through. We fabricated the keel lifting
mechanism ourselves and it welded up ok if a little untidily.
The old mast was put in position
and rigging lengths measured and new rigging ordered. Once keel was in the
boat with the bulb on we realised we couldn’t raise the mast as we expected
as to fit the heel bolt to the mast it would have to already be raised to
about 45 degrees. First thoughts were that we will only raise mast once on
water with keel lowered sufficiently for top to be flush with the decks.
Wiring went well and all
instruments both old and some new work fine.
A yacht surveyor was called in for
insurance purposes and the boat was deemed fine with some minor changes to
get complete clean bill of health, such as second jubilee clips on skin
fittings, extra packing around battery, coverings on protruding bolts in
coach roof (we had already started on these and called them ‘head savers’).
Topside painting turned out to be
the most unsatisfactory part of the build. We used two part epoxy paint but
failed to get a decent finish, probably due to cold weather and lack of
time, still there are plenty of coats and from a distance looks fine. Paint
finish has been augmented by vinyl stripe and Moondog logos.
Antifouling went on fine with hull
lifted onto special timber cradle (4 by 2 box structure) to get under the
cradle supports.
We have a different arrangement for
the sprit in that it runs in two short tubes, one on the foredeck traveller
and the second on a swivel next to the forestay, the forestay being a few
inches back from the stem. In haul and outhaul works the same.
8th April 2005
The boat trailed well behind a Golf
Estate and launching was no problem with boat floating perfectly parallel to
the antifoul line( We had used a laser level to mark out the line before
masking up to paint).
A problem was encountered by trying
to use a long shaft outboard, as per plan, straight onto the low part of the
transom. This did not work with the prop cavitating 95% of the time. We have
now invested in a lifting outboard bracket bolted to the transom which not
only works well but saves damaging paint and varnish finish on the transom.
We had to scratch from the first
race (Saturday 9th April) as the mast was not raised in time and there were
still a number of fittings to add. We managed to complete these tasks on the
first race day such that on Sunday 10th we went out for the first sail.
Initial impression, under outboard, were of a hull that is very easily
driven making very little wash, over 5 knots achieved using a 4hp outboard.
We are using the main and #3 from
our old quarter tonner although both sails are as new Kevlar. Boats speed
under main and headsail seemed good and then we ventured to hoist the Code
Alpha asymmetric and speed leapt quite considerably. The boat handles very
well, nice and light on the helm and fast, whether this is fast enough to
compete on the IRC rating of 0.991 remains to be experienced however this
will be fast and fun!
Total man hours to get the boat to
the water in sailing trim was 982 and I know just a few were not recorded.
We also spent around £4000 on
construction, fittings, paint and epoxy remembering that many items were
taken from the old quarter tonner. Don’t forget cost of suryeyor and
insurance!
Only sails we have bought so far
are two asymmetrics, a code alpha and an APR90. It is likely that we will
need a lighter weather headsail as a #3 is too flat and too heavy a cloth
for the light stuff. Later this year we will get the boat officially
measured with the hope that the rating will reduce.
The first two race results have
been a bit disappointing however the first was an extremely light weather
affair and the second had a drifting patch in the middle of the race. During
the second race there was a super beam reach of around 10 knots apparent and
consistent over 9 knots of boat speed peaking in the high 11knots. All the
time the boat was stable and well balanced. We can’t wait now for a cross
channel beam reach blast! |